Projects

Mulanga Consulting

The rehabilitation of street and storm water

1 Month

Eskom Duvha Power Station in Witbank

Siemens For New Build Plant Kusile Power Station

Cold commissioning of the dry type transformers and SIPROTECT relay (7SJ64) in the LV switchgear incomer, Insulation testing on the LV switchgear boards, @ Kusile Power Station

1 Year

SIEMENS EA for replacement of Gen Protection @ Eskom Duvha Power Station

Designing of the generator protection schemes, do FAT, site commissioning and compile hand over documentation for Unit 3, Unit 4, Unit 5 and Unit 6 @ Duvha power station
The generator rated 630MW in each unit

3 years

SIEMENS EA for replacement of Gen Protection @ Eskom TUTUKA Power Station

Designing of the generator protection schemes, do FAT with Client (Eskom), site commissioning and compile hand over documentation for Unit 1, Unit 2, Unit 3, Unit 4, Unit 5 and Unit 6 @ TUTUKA power station.
The generator is rated 630MW in each unit

2 Years

TERNIENERGIA S.p.A

Services Including, Engineering Technical Support on Protection, re-commissioning of 33kV Switchgear, 33/132kV transformer protection schemes and line diff protection scheme. Update the drawing, protection settings. Configuration of the meters and plant incident investigation then compile incident report. After completing of the task we compile hand over documentation for plant @ TOM BURKE in Lephalale (Limpopo province) and PALEISHEUWEL in cape

4 Months

SIEMENS EA for replacement of 11kV & 3.3kV MV Switchgear Protection @ Eskom Duvha Power Station

Designing of the MV Switchgear protection schemes, do FAT with client (Eskom), and compile electrical documentation for Unit 1 - Unit 6 & Outside plant @ Duvha power station with each unit generating 600MW.

1 Year

SIEMENS EA for Fault Recorder @ ARCELORMITTAL SOUTH AFRICA

Configuration of the fault recorder and commissioning using PAS PQA

1 Month

TWINSARVER Group for replacement of protection relay and recommissioning of 6,6kV Switchgear

TWINSARVER Group for replacement of protection relay and recommissioning of 6,6kV Switchgear

Compile the Functional Description Specification
Factory Acceptance Test
Engineering Commissioning

6 Months